The Building Safety Act 2022 received Royal Assent on 28 April 2022, with provisions coming into force in stages across a series of commencement regulations throughout that year and into 2023. Its full weight, however, did not land until October 2023, when the new dutyholder regime and higher-risk building controls became live.
For those working on higher-risk buildings, whether in cladding remediation, fire stopping, or structural upgrades, it changed what compliance looks like from the ground up. Three years in, patterns are emerging. Some firms have adapted well. Others are still catching up.
For US companies working alongside UK partners, or those bidding on life-safety projects in England, getting familiar with this legislation matters. Here is what has changed, what has proven harder than expected, and where the real compliance pressure sits.
What “Higher-Risk Buildings” Actually Means
During the design and construction phase, a higher-risk building (HRB) is any residential building, hospital, or care home that is at least 18 metres tall or has at least seven storeys. For residential buildings, the threshold only applies where the building contains at least two residential units.
Hospitals and care homes are excluded from the in-occupation duties under Part 4 of the Act, meaning the HRB regime for those building types applies during construction only.
At the HRB threshold, a completely separate regulatory regime applies, overseen by the Building Safety Regulator (BSR). Having previously operated within the Health and Safety Executive since its establishment in 2021, the BSR became a standalone non-departmental public body under the Ministry of Housing, Communities and Local Government in January 2026.
For HRBs, building control applications can no longer go to local authorities or private inspectors. Everything goes directly to the BSR. That shift alone has caused significant delays on some projects, with industry reports of extended wait times for approvals at each of the three statutory gateways.
The Gateway Process: Where Projects Get Stuck
The gateway regime is the single biggest operational change for contractors. There are three checkpoints. Gateway one sits at the planning permission stage and requires the submission of a fire statement, setting out how fire safety has been considered as part of the planning application.
Gateway two must be cleared before construction begins, the BSR needs to approve designs before a spade goes in the ground. Gateway three is the completion stage, where the building cannot be occupied until sign-off is granted.
In practice, gateway two has caused the most friction. Dutyholders must submit competence declarations, detailed plans, and evidence that everyone on the project team meets the required standards. Any changes during construction need to be formally notified, recorded, and managed through a construction control plan. Firms that underestimated the documentation burden have found themselves stalled.
Dutyholder Roles and What They Require
The Act introduced a structured dutyholder framework that uses the same terminology as the CDM 2015 roles, client, principal designer, principal contractor, designer, and contractor, but the two frameworks are entirely separate and run in parallel.
The CDM roles focus on managing health and safety risks during construction, while the Building Regulations dutyholder roles focus on ensuring compliance with Building Regulations throughout design and construction. Previous CDM experience alone will not satisfy the competence requirements under the Building Safety Act regime.
Dutyholder Competence
Competence is the thread running through all of it. Every dutyholder must be able to demonstrate the right skills, knowledge, experience, and behaviours for their role. Clients cannot contract out of their obligation to verify this.
In practical terms, that means keeping records of competence assessments throughout the project lifecycle. For higher-risk building work specifically, clients must also ask whether prospective appointees have been subject to a serious sanction in the last five years and consider any related information before making an appointment.
How Training Providers Are Responding
Demand for structured Building Safety Act training has grown considerably since October 2023. Providers such as Morson Nexus offer dedicated eLearning courses covering the Act’s key provisions, aimed at directors, contractors, designers, and anyone implementing the legislation on live projects.
The shift towards formal, documented training reflects a broader industry push to turn awareness into demonstrable competence, which is exactly what the BSR expects dutyholders to show.
The Golden Thread: Documentation as a Legal Requirement
One of the most significant practical changes is the golden thread, the requirement to maintain a continuous, accurate record of building information throughout design, construction, and occupation. For fire stopping and cladding work in particular, this means every decision, every product substitution, and every inspection needs to be logged and traceable.
This is not just good practice. It is a legal obligation, and the BSR has the authority to demand documents and halt works if records are not in order. Firms used to keeping records informally have had to overhaul their document management processes entirely.
In Closing
Three years in, the Building Safety Act has moved the goalposts permanently. The dutyholder regime, gateway process, and golden thread requirements have added real complexity to projects involving higher-risk buildings. That complexity is manageable, but only for teams that have put the work into understanding what is required of them.
For anyone working on or near HRB projects in England, the message from the BSR is consistent: competence must be demonstrable, documentation must be maintained, and there is no longer any room for informal assumptions about who is responsible for what.