A major modernization effort is set to reshape one of Southern California’s most important freight corridors. Skanska announced it has secured a $534 million contract from the California Department of Transportation for the Vincent Thomas Bridge Deck Replacement Project through a joint venture with California Engineering Contractors.
The three-year project will include a phased deck replacement on the Vincent Thomas Bridge, which spans the main channel of Los Angeles Harbor and serves as a critical freight and commuter link along State Route 47 to the Port of Los Angeles and the South Bay region. The bridge will be closed for approximately sixteen months during construction.
The modernization will replace the aging deck with high-performance precast, prestressed concrete panels engineered for extended service life, improved load capacity and resilience against saltwater spray and corrosive coastal winds. The scope also includes new expansion joints, corrosion-protection systems and the integration of real-time structural health monitoring technology.
“Delivering this critical infrastructure allows us to apply advanced engineering solutions that improve safety for the traveling public, modernize essential bridge components, and help Caltrans maintain a vital economic corridor serving Terminal Island,” says James Bailey, Executive VP of Skanska USA Civil’s West Coast operations.
Leveraging the Construction Manager/General Contractor delivery model, the Skanska-CEC joint venture will utilize precision demolition, modular deck installation and advanced scheduling to minimize environmental and community impacts.
Construction is scheduled to begin in spring 2026, with completion anticipated by March 2029 and the bridge reopening in the first half of 2028.