How Contractors Are Navigating tariffs, Pricing Pressure and Project risk

How Contractors Are Navigating tariffs, Pricing Pressure and Project risk

You submitted that bid 8 months ago.

Steel was running where it had been for two years. You priced it accordingly, built in a reasonable contingency and won the job. Fixed price. Good client. Workable timeline.

This week your supplier sent a revised quote. Steel mill products are up 20.7% year-over-year. Aluminum is up 33%. Copper and brass are up 15.7%. Framing lumber is at $872 per thousand board feet, up roughly 13% from where you budgeted. That’s before the tariff layer—50% on steel, aluminum and copper; 10% on softwood lumber.

The job you won is the job you’re losing money on.

You’re not alone. An AGC-NCCER survey found that 43% of general contractors have cancelled, postponed, or scaled back at least 1 project in the past six months, with material costs cited as the direct cause. Nonresidential construction input costs ran at a 12.6% annualized rate in January and February of 2026—the fastest pace since the supply-chain peak of early 2022, per Engineering News-Record’s Q1 2026 Cost Report.

Every owner in your market is reading the same numbers. Most are doing the same thing with them: measuring the damage, calculating the exposure and waiting to see what happens next.

That’s understandable. It’s also the wrong response—not because you’re uninformed, but because measuring what’s happening and managing through it are two entirely different things.

The Thermometer and the Thermostat

Here’s a framework I use with clients when markets turn volatile.
A thermometer tells you what the temperature is. Accurate, useful, completely passive. When the environment shifts, it shifts with it. That’s all it does.

A thermostat holds a temperature. It’s set to a target, and when conditions drift from that target, it activates. It doesn’t report the environment—it responds to it, until things return to where you decided they need to be.

Most construction businesses run like thermometers. They watch the material market, track last quarter’s margins, adjust pricing after the fact. In a stable environment, that’s fine.

It stops working when input costs move 12.6% in 2 months.

iStock 1811581032The 3 Things Your Thermostat Needs

A thermostat isn’t a mindset. It’s a system. And it only works when all three parts are in place.

Lines in the sand. These are the numbers your business needs to stay profitable. Not goals—floors. The point at which something has to change. Right now, for a construction business, those lines might look like:

Gross margin by contract type: fixed-price work must stay above 18%
Material cost ceiling by input: the steel price at which my contingency on active bids is gone
Backlog coverage: below 14 weeks of signed work, business development activates immediately
Bid variance: if a supplier quote comes in more than 12% above my estimate assumption, that bid doesn’t go out at the original number

These aren’t targets you’re hoping to hit. They’re the lines you’ve decided to defend.

Signals. A signal tells you a line has been crossed. The critical thing is that you define the signal before the market moves—so you’re not deciding in the moment whether things are serious enough to act. You already decided that. The signal fires and a response happens.

Signals for a construction business right now:

  • A supplier quote that exceeds your material assumption by more than your defined threshold
  • A contract’s gross margin dropping below your floor during execution
  • Backlog coverage falling below your minimum
  • A tariff change that touches a material category sitting in your active bids or submitted estimates

A predefined response.

This is where most businesses stop short—and it’s the whole point of the system. When a signal fires, you shouldn’t be deciding what to do. You should be executing what you already decided when you were thinking clearly, before the pressure was on.

Here’s what that looks like right now:

  • Steel exceeds your threshold: Every new bid includes an escalation clause. Existing fixed-price contracts with steel exposure get a renegotiation call initiated within five business days. Not when it feels right—within five business days.
  • A contract’s gross margin drops below your floor: Owner reviews it within one week. A client conversation happens. It does not get quietly absorbed while you hope the next job makes up for it.
  • Backlog drops below your minimum: Stop waiting for inbound work. Start calling your relationship list. Today.
  • A supplier quote comes in more than 12% above your estimate: That bid doesn’t go out at the original price. It gets repriced, rebid with a different material spec or includes a written contingency the client has to acknowledge before you proceed.

The predefined response is what separates a thermostat from good intentions. The lines in the sand and the signals are preparation. The predefined response is the actual protection.

Let Me Show You What This Looks Like

I worked with a mechanical contractor earlier this year who had drawn exactly these lines. When the tariff announcements hit in early 2026, he didn’t call a meeting to figure out how bad it was. He pulled up the response he’d written six months earlier and started making calls.

Within 10 days, he’d initiated renegotiation conversations on three fixed-price contracts, added escalation clauses to two of them and adjusted his bidding assumptions going forward. His clients heard from him before they had time to wonder what was happening.

That’s not luck. That’s a system.

The contractor in the next county—same market, same material exposure—spent those same 10 days in reactive conversations he wasn’t prepared for. One of those clients is now in dispute. The relationship may not survive it.

Same tariff environment. Different outcomes. The difference was the work that got done before the signal fired.

What Most Contractors Are Doing Right Now

Scrambling. The revised quote hits the estimator. The estimator goes to the project manager. The project manager goes to ownership. Everyone calculates how bad it is. Someone calls the client. The client pushes back. An uncomfortable conversation happens under pressure, with no framework for how it should go, at a moment when the relationship is already strained.

Meanwhile, the pipeline of bids from the past six to 12 months sits unreviewed. Nobody has gone through contract by contract to figure out which ones are underwater and by how much. That review feels like it can wait—until it can’t.

And the second-order effects catch them off guard. Flooring contractors and product suppliers serving commercial construction will feel project delays in their installation volume on a three- to six-month lag. The pipeline thinning doesn’t show up in your backlog today. It shows up in your schedule four months from now, when there’s far less room to respond.

Do This Now

You don’t need new software to start. You need a working document and three hours.

Step 1: Draw your lines in the sand.

Write down the floor for each variable your margins depend on. At minimum:

  • Gross margin floor by contract type
  • Material cost ceiling for your top three input categories
  • Backlog coverage minimum in weeks
  • Maximum variance between your estimate assumption and an incoming supplier quote before a bid gets repriced

Step 2: Define your signals.

For each line, write the specific, observable event that tells you it’s been crossed. “Steel prices are high” is not a signal. “My supplier’s steel quote exceeds $X/ton” is a signal. Be precise enough that there’s no debate about whether it fired.

Step 3: Write the response before you need it.

For each signal, define exactly what happens:

  • Who gets notified, and within what timeframe?
  • Which client conversations get initiated—and who makes the call?
  • What changes on bids going out this week?
  • What gets escalated to ownership versus handled at the project level?

Post it where your team can see it. Review it quarterly. Update the lines when your cost structure changes.

Your Suppliers Are Feeling This Too

If you supply into commercial construction—flooring, specialty products, anything tied to project timelines—run the same diagnostic on your manufacturing clients right now. 32% of manufacturing leaders say they’ll pass 100% of tariff increases directly to customers.

Another 42% are splitting it—some passed on, some absorbed. That repricing is hitting their customers now, which means the volume assumptions they built their 2026 plans around may already be wrong—and yours, downstream of them, may be too.

What’s your line in the sand on their order volume? What’s the signal? What’s the response when it fires?

The Question Worth 3 Hours

Tariffs may ease. Some of the postponed projects will restart. Conditions will shift in directions nobody is calling accurately right now.

The thermometer business will adjust when they do. The problem isn’t whether it adjusts—it’s what the adjustment costs when it happens after the fact, under pressure, without a framework for the conversation.

The thermostat business already answered the harder question: What does this company need to stay profitable—and what happens, specifically and immediately, when the environment moves away from that?

Most owners can answer the first question. Fewer have a working answer to the second.

If you’re reading this and recognizing the gap—lines you’ve never drawn, signals you’ve never defined, responses that exist only in your head—that’s a three-hour problem, not a year-end problem. I work with mid-market construction and supply businesses on exactly this kind of work.


Jane Gentry founded JaneGentry & Company after 25-plus years consulting for and running businesses struggling through the same market volatility she writes about. She works with mid-market CEOs across manufacturing, construction, logistics, and professional services—as someone who has carried the P&L through a volatile market, not just advised on it. Reach her at jane@janegentry.com.

 

Share this post :

Facebook
Twitter
LinkedIn
Pinterest

Stay close to the industry.

CCR updates, digital magazines, events, and partner insights.

Current Issue — CCR #10

Editorial & Third-Party Content Notice: Articles, press releases, company announcements, and accompanying media (including photography, graphics, and video) published on this site may be provided by third-party contributors, PR representatives, or wire sources as cited. Authorship and original copyrights remain with their respective holders.

Commercial Construction & Renovation is a registered service provider under the Digital Millennium Copyright Act (DMCA). To submit an inquiry, copyright claim, or formal takedown request, you may view our registered agent listing and official contact details via the U.S. Copyright Office DMCA Designated Agent Directory, or contact our compliance desk directly at publisher@ccr-mag.com.

Receive the CCR 2024 Idustry Report

Get ahead of your Competitors with CCR's FREE Industry Insider's Report 2024!

Always stay two steps ahead of your Competitors. Stay informed with the latest in the Industry. 

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

This site uses cookies to ensure that you get the best user experience. By choosing “Accept” you acknowledge this and that ccr-mag.com operates under the Fair Use Act. Furthermore, Changing privacy laws now require website visitors from EEA based countries to provide consent in order to use personalized advertising or data modeling with either Google Ads & Analytics. Find out more on the Privacy Policy & Terms of Use Page and our Editorial & DMCA Notice.