On a great many commercial projects, the entry gate is given roughly one line in the specifications. Typically, it reads “custom ornamental gate per design intent, see elevation,” accompanied by an attractive rendering in the drawing set. That approach tends to hold up until the fabricator begins asking questions, at which point it is often unclear whether the structural design, the operator, the conduit or the footings fall within anyone’s scope.
Custom gates sit somewhat awkwardly between trades. They are part architectural metalwork, part structure, part access control and part electrical work, and for this reason a vague brief frequently results in RFIs, change orders and a gate that arrives several weeks after the rest of the site work has been completed. A clearer brief at the outset prevents most of these problems, and the items below are the ones most commonly left out.
Start with the opening, not the artwork
Before patterns are discussed, the brief should establish the clear opening width and height, the method of operation (single swing, bi-parting swing or slide) and the direction in which the gate opens. Grade is generally given less attention than it deserves. In the case of a swing gate on a drive that rises toward the property, the leaf may not clear the paving at all, whereas a slide gate requires a length of fence or wall beside the opening that is at least equal to the opening itself, plus room for the counterbalance on cantilever designs. Typical gate widths for different vehicle types should also be confirmed at this stage.
Where pedestrians will use the entrance, a separate pedestrian gate should be shown on the drawings. Automated vehicle gates are not intended to serve as walkways, and adding a pedestrian gate late in the process usually means the fence layout has to be reworked.
Decide who is designing the structure
A large number of scope gaps can be traced back to this point. The brief should state clearly whether the gate, posts and footings are to be designed by the engineer of record or delegated to the fabricator and, in the case of delegation, what the submittal is required to contain. The VA guide specification for decorative metal fences and gates provides a useful model, as it calls for delegated-design drawings and calculations signed and sealed by a registered design professional, with loads based on ASCE 7.
Wind is the load most often underestimated. A solid or tightly spaced privacy panel behaves in much the same way as a sign, and a large swing leaf places considerable load on its hinges and post when a gust catches it partly open. The design wind criteria should therefore be stated, or at least the standard and exposure category the fabricator is expected to use, and post size and footing depth should not be left to the field.
Materials, members and welding
The terms “steel” and “aluminum” serve as starting points more than as specifications. The brief should identify the grade or alloy, the minimum wall thickness for frame members, the welding standard (AWS D1.1 for structural steel or D1.2 for aluminum, for example) and the hardware, including hinge type and capacity, latches, drop rods for bi-parting leaves and positive stops. Where stainless hardware will come into contact with aluminum or galvanized steel, the method of isolating the dissimilar metals should be noted as well, since this detail is easily overlooked and costly to correct once corrosion has begun.
Treat the finish as a system
A specification that simply reads “black powder coat” leaves almost every decision affecting durability to whoever carries out the coating. On exterior steel, the practical differences between powder coating and wet paint become apparent after a few seasons of UV exposure, road grit and the occasional stone chip, and they generally appear first at edges and welds.
For this reason, the brief should describe the complete system: the surface preparation (an abrasive blast to a named SSPC standard, such as SP 10 near-white), the primer and the chemistry of the topcoat. Zinc-rich primers are widely used on steel because the zinc corrodes sacrificially and prevents rust from spreading beneath a chip. In the case of aluminum, a reference to AAMA 2604 or 2605 establishes a clear performance requirement. It is also advisable to request finish samples on the actual substrate and to include touch-up requirements for damage that occurs during installation.
Automation and the scope gaps around it
Where the gate is to be automated, the brief needs to make clear who furnishes the operator, who installs it and who is responsible for power, conduit and the access-control interface. These scopes are often split among three subcontractors, and when nobody takes ownership of the coordination, the gate may arrive on site without the conduit stub-ups it requires.
The UL 325 usage class the operator must meet should also be named. The standard distinguishes between residential, general commercial access, industrial or limited access and restricted access installations, which means a hotel entry or a multifamily garage will not fall into the same class as a private residence. The gate itself must also be constructed with automation in mind. The current edition of ASTM F2200 requires automated vehicular gate systems to comply with that specification as well as with UL 325, which brings in requirements such as guarded rollers, positive stops and limits on openings in slide gates.
Where a gate crosses a fire apparatus access road, the fire code official will also be involved. The International Fire Code expects security gates on such roads to be approved and to have an approved means of emergency operation, so that conversation is best started before the design is finalized.
Submittals and schedule
Shop drawings should show elevations, member sizes, post foundations, hardware and anchorage, together with the operator layout where applicable, and it is advisable to require them at an early stage. Custom gates are commonly a two-to-three-month fabrication item once drawings have been approved, and fabrication rarely begins before that approval; as a result, a slow review cycle can easily push the gate past the rest of the site work.
Putting it together
Most of these items require no more than a sentence or two each and taken together they rarely exceed a single page. That page is what allows a fabricator to price the gate accurately and build it correctly the first time, while keeping decisions about structure, finish and automation with the people who are accountable for them.