Commercial contractors do not usually fail on bad jobs. They fail in the middle of good ones. The bid was sound, the crews performed, the owner was satisfied—and somewhere between mobilization and the second draw, the account came up short while several hundred thousand dollars of perfectly good receivables sat on someone else’s approval schedule.
This is a structural feature of how commercial construction pays, not a management failure. But it is a feature that has to be financed deliberately, because it will not finance itself.
The Cash Timeline of a Job
Follow the money on a mid-size commercial project.
Mobilization comes first: materials, equipment, permits, bonding, crews on site. Payroll runs weekly from day one. Then the collection side begins and it begins slowly. Progress billing typically is monthly, submitted with lien waivers, certified payroll where applicable, and documentation that must be complete. The GC or owner reviews on their own timeline. Payment follows on contract terms after approval.
Realistically, work performed in week one is paid somewhere between day 45 and day 75. And the last slice—retainage, commonly 5% to 10% of the entire contract—is held until substantial completion or final closeout, often months past the last day of work. For many contractors, retainage is close to the whole profit margin on the job, held hostage to a punch list and a closeout package.
So the contractor funds one to two months of full job cost before the first dollar returns and waits considerably longer for the portion that represents the actual profit.
Bigger Jobs Make It Worse
Every contractor knows the pull of the job that changes the company. It also multiplies the float requirement. A project twice the size requires roughly twice the up-front capital carried across the same or longer collection timeline—and larger GCs and public owners tend to have slower, more documentation-heavy payment processes, not faster ones.
That is why contractors so often get in trouble on the job that made them, and why it happens in the middle rather than at the end. The revenue is real, the margin is real and neither has arrived yet.
The Multipliers
Three things widen the gap beyond its structural width.
- Change orders performed before approval – Work done, cost incurred, not billable. This is the single most common self-inflicted cash wound in commercial work, and it is almost always the result of schedule pressure rather than carelessness.
- Chronic slow payers – One GC with a consistent 60-plus-day approval cycle can quietly finance itself on your balance sheet across every job you run with them. Most contractors can name the offender but have never priced what the relationship costs.
- Seasonality – In most regions the season front-loads spending in spring while collections trail into summer, so the worst cash position of the year lands squarely in the busiest stretch.
Fix the Free Things First
Before any financing conversation, the levers that cost nothing:
Negotiate mobilization or deposit payments into the contract. It is a term like any other, and contractors who ask for it get it more often than contractors who assume they cannot.
Bill progress twice monthly where terms allow. Halving the billing cycle takes real days out of the timeline at no cost.
Submit complete pay applications the first time. A rejected application does not lose a week—it restarts the entire clock, including the GC’s review queue position.
Get change orders approved in writing before performing the work. Every experienced contractor knows this and a remarkable number still do not.
Track days-to-cash by GC—actual payment dates, not stated terms. The number usually identifies one or two relationships responsible for most of the strain, which turns a vague cash problem into a specific business decision.
Then Finance What Remains
When the gap persists after the operational fixes, several structures fit different parts of it.
Construction invoice factoring advances against approved progress billings, converting the wait into immediate capital and scaling automatically as you bill more. The terms that matter more than the rate: recourse, whether you must factor the whole book, and whether customers are notified.
Equipment financing belongs on equipment—cheaper, secured by the asset and it should never be funded out of working capital.
Revenue-based funding provides a lump sum against deposit history, repaid as a fixed daily or weekly remittance. It covers what factoring cannot: mobilization before anything is billable, a bond requirement or payroll through a slow approval cycle. Because it is underwritten on deposits rather than collateral or tax returns, contractors that banks decline routinely qualify, and it funds in days.
A bank line of credit, when obtainable, beats all of the above on cost. It is worth arranging when you do not need it, because the timeline to get one never matches the timeline of a cash crunch.
The Trap
The failure pattern that ends otherwise sound contractors is a chain of short-term positions: one to cover mobilization, a second to service the first, a third by the next job. The underlying gap never closed, so every new debit lands on deposits that have not accelerated.
The diagnostic is one number: combined daily debits divided by average daily deposits. Under roughly 15 to 20 percent is workable. Approaching 40% means the financing has become the problem, and the answer is restructuring what exists—not adding another position.
The Point
The gap between draws is not evidence that something has gone wrong. It is how commercial construction pays, and it has been that way for a very long time. The contractors who last are simply the ones who sized it, planned it, and financed it on purpose—before it financed them.