The Cathedral School for Boys, a private K-8 school, is affiliated with Grace Cathedral, a venerated San Francisco institution with an impressive architectural presence atop Nob Hill. Gresham Hall, however, the school’s cafeteria and auditorium space, exhibited none of the cathedral’s grandeur, despite its location directly below the nave of the soaring Gothic Revival landmark.
The Office of Charles F. Bloszies FAIA was challenged to renovate the space in a way that would modernize the facilities while creating an atmosphere worthy of the prestigious school and the historic Cathedral building it occupies. (Some will recall the firm’s sensitive, award-winning expansion from not long ago.)


Images Courtesy of: C.C. Sullivan
Archival research revealed clues about Gresham Hall’s original architectural features, which had been compromised or covered up in the years since their original construction in the 1930s. Bloszies’s renovation sought to celebrate these historic elements:
- The octagonal concrete piers that support Grace Cathedral’s primary structure above.
- The grand stair that had been hidden under a newer floor slab.
- The arched windows that were blocked by exit stairs or repurposed as mechanical openings or made into rectangular doorways.
The renovation, completed with leading contractor Truebeck Construction, revealed and restored these vestiges, incorporating them into the design as functional components with historic texture. The building’s concrete structure was left exposed, its rough board-formed finish hinting at its age. The stair was rebuilt following its original footprint, its lower treads spilling out into the remodeled space. The neo-Gothic windows were restored and exposed to the exterior once more, letting daylight into Gresham Hall for the first time in decades.



Images Courtesy of: C.C. Sullivan
The cafeteria kitchen was expanded, furnished with all new equipment, and enclosed with folding glass walls that run between the octagonal columns, allowing its serving area to be continuous with the adjacent dining space when open. The kitchen space is legible as a smaller module within Gresham Hall, which, in turn, makes the latter feel more spacious. A clear, logical circulation path leads students down the restored stair, into the kitchen, through the serving line, and into the dining area.
This first phase of the Gresham Hall remodel, focused on the kitchen and adjacent spaces, was completed in three months during the summer of 2026. Achieving the tight schedule required close coordination with the client and contractors prior to construction to meet deadlines for procurement and permitting, and constant communication during construction to resolve questions and conflicts quickly. The second phase consists of expanding and remodeling the larger dining area, bringing in still more daylight through windows on the façade opposite the kitchen, and emphasizing the space’s impressive height with a coffered wood ceiling. The phased approach adds complexity, but allows construction to proceed without disrupting the school during the academic year.

Image Courtesy of: C.C. Sullivan
The thoughtful interplay between historic and contemporary elements in the Gresham Hall renovation is consistent with The Cathedral School for Boys’ visual brand, and with its identity as a progressive institution with deep roots in its community. It also aligns with Bloszies’s design ethos, which seeks to enhance the appearance of both the old and the new through careful juxtaposition.
This project is the school’s third collaboration with the Office of Charles F. Bloszies FAIA to be constructed, in addition to several concept studies for future expansions now on the boards.